Cate School Project Home
Project Summary

Click images for full-size photos tracking the progress of this restoration project.

Archive:
Week 1     Week 2-3     Weeks 4-6     Weeks 7-10     Weeks 11-12


Weeks 2 & 3
September-October 2008

Cutting1     Cutting2
   
Cutting3     Pit 

Heavy machinery cuts soil out of the creek crossing to create a stable grade and prepare for the bridge supports.

  


  

Pit5     6Pit

  

7Pit     Framing 

The pits for the bridge abutments are further excavated and compacted to provide a stable substrate. 
Crews build wooden frames for the bridge footings. 

 


   
Pouring    Footing
The concrete mixers pour concrete to create the first layer of the bridge footings.
   


Archive:
Week 1     Week 2-3     Weeks 4-6     Weeks 7-10     Weeks 11-12