Raya Project
Project Summary

Click images for full-size photos tracking the progress of this restoration project.

Archive:
Pre-Construction     Week 1     Week 2     Weeks 3-4     Weeks 5-9    Weeks 10-13  

Weeks 10-13
December 2008-January 2009

Abutment     Abutments
     
The abutments are finished and prepared for the bridge to be installed. 
Water flow returns to the creek channel.

          
Crane     Install
   
The crane hoists the bridge sections over the creek and into the abutments.

   
Finishing      Finishing2
     
     Complete
  
Crews put the finishing touches on the bridge installation.  The finished product is a restored creek
that allows unimpeded steelhead trout migration.

    
Downstream1     Downstream2
    
Downstream3

A smaller Arizona crossing on the same property is removed and decommissioned.  Without a bridge replacement, the construction process is much easier.  This crossing is removed and the creek channel restored in only one day.

 

    
Archive:
Pre-Construction     Week 1     Week 2     Weeks 3-4     Weeks 5-9    Weeks 10-13

   


Home  Carp Creek  The Coalition

Projects  Documents  Links 

 ©Carpinteria Creek Watershed Coalition

Last updated Jan 14, 2009

 

Email

©Carpinteria Creek Watershed Coalition